How does progress-by option work in a target

Progress by option shows up in Timeseries type targets. Using Progress by, you can visualize how much progress has been made on achieving the target by month to date, by quarter to date, by half-year to date, or year to date. 

Steps to do group by

  1. Select Set Targets (both in Territory Design, and Team Design)
  2. Select the Targets tab.
  3. From the Target Operations Menu (the three vertical dots) on the right of your Timeseries target, pick Progress by. 
  4. Select Progress by month to date, by quarter to date, by half-year to date, or year to date.
  5. You'll be able to see a pie chart changing its value as long as you change your selection under progress-by.

Did this answer your question? Thanks for the feedback There was a problem submitting your feedback. Please try again later.

Still need help? Contact Us Contact Us